Building Schedule
Activity Start End Range Diff
Frame complete
Install fireplace, plumbing/gas top outs, bathtubs, ext windows and doors Low 5/2 5/6 5/10 5/22 4 - 16
High 5/2 5/13 5/10 5/22 -3 - 9
Roof Complete
rough HVAC, Electrical, windows complete, exterior paint prime Low 5/6 5/17   -  
High 5/16 6/3       -  
Pre-sheetrock inspection
insulation, mechanical inspection, gas line, garage door installed, HRick exterior Low 5/17 5/21   -  
High 6/6 6/24       -  
Sheetrock complete
doors, moulding, closets, mantle, tile bath, hearth, paint exterior Low 5/21 5/25   -  
High 6/27 7/8       -  
Interior trim
blown insulation, enamel, interior prime, vinyl, cabinet, counters/backsplash Low 5/25 5/29   -  
High 7/11 7/22       -  
Cabinets, counters complete
mirrors, shower doors, final grade, order appliances Low 5/29 6/2   -  
High 7/25 8/5       -  
Final mechanicals
HVAC, plumbing, electrical, front door, hardware, appliances, flooring, fence, landscaping, paint, clean Low 6/2 6/6   -  
High 8/8 8/19       -  
Move in inspection
  Low 6/6 6/10   -  
High 8/22 9/2       -